Approval of Change Order No. 1 Final to BL110-17, Pharr Woodberry GS Extension and Sewer Service Expansion with Strickland & Sons Pipelines, Inc., increasing the contract by $456,725.19 and extending the contract completion time by two hundred seventy four (274) days. The contract is adjusted from $3,747,296.00 to $4,204,021.19. Subject to approval as to form by the Law Department. (Staff Recommendation: Approval)