Approval/authorization for Chairman to execute
Supplemental Agreement No. 1-Final with Gary's Grading and
Pipeline Co., Inc., for Temple Johnson Road (west of Big Haynes
Creek-west of Summit Place) project, M-0360, and Lenora
Church Road at Centerville Rosebud Road No. 2 project, M-0575,
total increase $7,019.78, total reduction $229,104.92, revised
contract amount $1,201,959.40. Approval for Chairman to
execute any and all related documents, subject to approval by Law
Department. This is the final change order for this contract. This
contract is funded by the 2005 SPLOST Program. District
3/Hunter (Staff Recommendation: Approval)