Approval/authorization for the Chairman to
execute change order no. 1-final to the contract with Abatech
Services, Inc. increasing the contract amount by $499,845.00 for
work associated with the DWR Facility Demolition-Phase I
(Duluth Water Intake Pump House, Beaver Ruin WRF, Jack's
Creek WRF, No Business Creek WRF and Northwoods
Maintenance Facility). The contract amount is adjusted from
$720,000.00 to $1,219,845.00. Subject to approval by the Law
Department. This project is funded by the Water and Sewer
Renewal and Extension Fund. District 1/Brooks, 3/Hunter and
4/Heard (Staff Recommendation: Approval)